Ongoing Projects
The Afghanistan Railway Authority projects for which the studies have been completed and the provisions through the Government, Regional and International Collaboration that are likely to be considered for fast track execution of the following approved projects under ANRP:
Afghanistan National Railway Plan(ANRP) Ongoing Projects | |||||||
No | Project Name | Project Status | Project Location(Province) | Total Length(km) | Procurement Status | ||
Prefeasibility Study | Feasibility Study | Details Design & Construction | |||||
1 | Khaf-Herat 4th Section First Phase | Complete | Complete | Planned for 2018 | Herat | 43 | Ongoing |
2 | Khaf-Herat 3th Section | Complete | Complete | Planned for 2018 | Herat | 62 | Complete |
3 | Reconstruction and Renovation of the Torghundi Port | Complete | Complete | Planned for 2018 | Herat | 13 | Complete |
4 | Construction of Sub-lines of the Aqina Railway Station | Complete | Complete | Planned for 2018 | Faryab | 10 | Started |
5 | Construction of Balk Administrative Building | _ | _ | Ongoing | Balk | _ | Ongoing |
6 | Construction of Herat Administrative Building | _ | _ | Ongoing | Herat | _ | Ongoing |
7 | Extension of Power Cable & Installation of Transformer for Rozanak Station, Khaf-Herat Railway | _ | _ | Ongoing | Herat | _ | Complete |
8 | Construction of Shade & Surroudings of 3th Section of Khaf-Herat Railwy | _ | _ | Ongoing | Herat | _ | Complete |
9 | Preparation & Installation of Solar Power for Ghorian, Shemtig Station & Khaf-Herat 3th Section Border | _ | _ | Ongoing | Herat | _ | Ongoing |
10 | Provision & Shifting of Needed Equipment and Conex of the 3th Section of Khaf-Herat Railway | _ | _ | Ongoing | Herat | _ | Complete |
11 | Purchasing Railway Maintenance Equipment | _ | _ | Ongoing | Herat | _ | Ongoing |